The constraint
The construction is a few weeks. The exhaust route, the trade waste agreement, the food business notification and the gas or power upgrade are not, and none of them is ours to accelerate.
Every hospitality project we have seen fail on programme failed on the same thing: the operator signed a lease, set an opening date, and then discovered that the exhaust could not be discharged where it needed to go, or that the trade waste agreement had a queue in front of it, or that the tenancy did not have the gas supply the menu assumed.
The kitchen
the part you are paying us to build
Kitchen exhaust discharge
A route to atmosphere, and usually a landlord or neighbour conversation
Grease arrestor and trade waste
An agreement with the water authority, on their timetable
Food business notification
Council, with its own fit-out requirements and inspection
Electricity and gas supply
Upgrades are applications, not site work
The rest of the venue
What else decides a hospitality programme.
- Acoustics and the licence
- A planning permit or liquor licence commonly carries noise conditions, and those conditions become a construction specification. Glazing, ceiling treatment, plant selection, door seals and where the speakers can go. A venue that cannot meet its noise condition cannot trade the hours it planned to.
- Mechanical make-up air
- A kitchen exhaust that removes air needs air replaced, or the front of house becomes unpleasant and the doors will not close properly. It is the most commonly under-designed element in a small venue.
- Grease, waste and cleaning
- Trade waste, grease arrestor location and access for pump-out are decided by where they can physically go, which is often not where the design wanted them.
- Front of house finishes
- Hospitality finishes carry the shortest life and the tightest visual tolerance of anything we build. Joinery lead times routinely exceed the construction period.
- Accessibility and amenities
- Accessible sanitary facilities, path of travel and counter heights are code matters that get squeezed by a layout designed around covers. Better resolved at concept.
- Fitting out around a live venue
- Refurbishing a trading venue means overnight works, hygiene separation and returning the space to service every morning. It is possible and it is not cheap.
What decides a hospitality programme
Three approvals, and none of them is the building permit.
- Mechanical exhaust and make-up air
- A commercial kitchen needs an exhaust path to a discharge point, and that path usually crosses property the tenant does not control. Where it goes, what it sounds like at the neighbour’s window and whether the landlord will permit the penetration are questions to settle before the layout is fixed, not after.
- Trade waste and grease arrestor
- The water authority sets the arrestor size and the discharge conditions, and the arrestor has to go somewhere with vehicle access for pump-out. It is a siting decision with a lead time, and it has moved more kitchen layouts than any designer has.
- Food, liquor and council approvals
- Food business registration, liquor licensing and any planning consent for hours or outdoor areas run on their own timelines. We track them as programme items with named owners and dates, because a finished venue that cannot legally trade is the one outcome nobody budgets for.