The constraint
The workplace half is straightforward. The half with the equipment in it is where the programme and the services capacity actually go.
Those rooms bring dedicated cooling, dedicated power, containment, acoustic separation, vibration and access control. Each of them draws on base building capacity that has to be confirmed in writing, and each of them carries a lead time that the workplace half does not.
One lease, two buildings
The workplace half
Open plan, meeting, collaboration, end-of-trip, front of house
Large area · Light services · Short lead time
The technical half
Comms and server rooms, test benches, secure areas, labs
Small area · Heavy services · Long lead
Base building capacity
Cooling, riser, condenser locations, structural allowance. Confirmed in writing, before design.
Rarely the constraint
A well-understood fitout with known trades and ordinary lead times. It follows the other half.
Sizing the room
Start at the equipment, finish at the room.
Nearly every comms room problem we are called into started with someone nominating a room on a plan before anyone had added up what was going into it.
Sizing a comms room, in sequence. Start from the equipment the client will actually install, which gives a heat load in kilowatts. The heat load sets the cooling, the cooling needs a condenser location which is a landlord question, and the equipment plus the cooling together set the electrical load. The electrical load has to be reconciled with the riser capacity, and only then is the room size and containment resolved. Skipping to room size first is the common error.
Size the room last, not first
1
Equipment list
from the client, not assumed
2
Heat load
in kilowatts, at capacity
3
Cooling
dedicated, not the floor system
4
Condenser location
a landlord question, always
5
Electrical load
equipment plus cooling
6
Riser capacity
confirmed in writing
7
Backup and UPS
runtime the business needs
8
Room and containment
the answer, not the question
The common error is starting at step eight. A room is nominated on a plan, the equipment arrives, and the cooling has nowhere to reject heat to.
The condenser location is a landlord conversation and it is the one step in this chain that a tenant cannot solve on their own.
The technical half
What each of those rooms actually needs.
Dedicated power
Its own circuit, often backed up, sized from the equipment rather than from the floor area.
Dedicated cooling
A high heat load in a small room, with a condenser that needs somewhere to reject to.
Access control
Tied to the base building system, with cabling segregation where a customer requires it.
Containment and growth
Cable containment sized for what comes next, because the second fitout costs more than the spare tray did.